Four ships have taken on gas at QCLNG

MORE than a month into exporting gas, the QCLNG berth at Curtis Island has handled four ships.

The fourth fully loaded vessel departed last week and the fifth is due to arrive at the weekend.

That number is consistent with QGC's planned schedule for the commissioning phase of the first production train.

When the plant is at full production capacity next year, up to 120 vessels per year on average will visit QCLNG.

Bechtel will continue working on QCLNG throughout 2015 to finalise commissioning and production testing of the LNG processing Train 1, and to finalise construction and then commission Train 2 in the second half of the year.

A company spokesman said the LNG companies with housing facilities used for fly-in fly-out workers on Curtis Island were working with government authorities to assess a number of options to house contract workers that would be required for maintenance from time-to-time.

Topics:  bechtel curtis island gas gladstone lng qclng


Stay Connected

Update your news preferences and get the latest news delivered to your inbox.

Region faces wild wind

DESTROYED: Half of the roof of the Moranbah home was ripped off from the 104km/h wind.

Moranbah residents say weather is worse than the cyclone.

Heroic rescue saves life

CLOSE CALL: Leslie Cruthers and Buddha at the spot the playful pup fell into the Nogoa River.

Kayakers rush to save dog walker clinging to riverbank.

National super star at age 13

Competing in Rotorua, New Zealand earlier this year.

Dingo local takes on international motocross competition.

Local Partners