NBN Co rejects reports of delays, budget blow-out

THE National Broadband Network has rejected reports it is behind schedule and over budget.

An internal NBN Co report leaked to media yesterday showed the company had only completed the design of 662,665 individual projects - 750,000 short of the 1.4 million due now.

The internal report also referred to an increase in connection costs for homes under the network, rising 22% to $1366 from the original target of $1114.

But NBN Co rejected the claims, saying it had "met or exceeded every target for six quarters in a row".

It also said it was on track to achieve its target of 2.6 million homes "ready for service", one million homes using the network and revenue of $300 million.

Labor frontbencher Jason Clare warned he believed the cost of the network had doubled and the time it would take to build could almost double.

The company said more than 800,000 homes were using the network and up to 1.8 million homes could order a service.

Topics:  internet national broadband network nbn nbn co

Stay Connected

Update your news preferences and get the latest news delivered to your inbox.

A family fun day for all

GET INVOLVED: This year's St Joseph's family fun day will have a range of unique activities for all ages.

Support St Joseph's in Clermont at their annual Family Fun Day.

Blackwell comes to CH

IN TOWN: Aussie cricketer Alex Blackwell will be   a   speaker at Emerald's Epic Street Party on March 22.

Alex Blackwell will be a guest speaker in Emerald next week.

Step back for local graziers

DISAPPOINTED AND DISGUSTED: Member for Gregory Lachlan Millar and farmer/grazier Ian Sampson.

Proposed legislation raises ire on local farms.

Local Partners